Scheme Details
DISTRICT
Etawah
AGENCY
OMIL-JWIL (JV)
SCHEME ID
20097780
SCHEME NAME
KHIRITI
ESTIMATED COST
156.87
EXPENDITURE
67.85
AUTOMATION STATUS
Not Integrated
SCHEME STATUS
Under Construction
Scheme Physical Progress
Village Coverage
Village Covered
1
T/W Progress
Required
1
Boring Done
1
Air Compressor Done
1
O.P. Unit Done
1
OHT Progress
Required
1
Work Started
1
Work Completed
0
Solar Plant
Required
16
Procured
16
KW
Work Status
Yes
Electric
Required
0
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
4319.00
Meter
Length Laid
4265.00
Meter
Scheme Assigned Villages
Village-wise FHTC, Har Ghar Jal and Certification Status
1 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Etawah | Chakkarnagar | Khiriti | 420110 | Khiriti | 210 | 210 | 100% | Har Ghar Jal | Not Certified |