Scheme Details
DISTRICT
Gautam Buddha Nagar
AGENCY
LC INFRA
SCHEME ID
20097841
SCHEME NAME
KUDI KHERA VILLAGE WATER SUPPLY SCHEME
ESTIMATED COST
264.62
EXPENDITURE
216.49
AUTOMATION STATUS
Not Integrated
SCHEME STATUS
Under Construction
Scheme Physical Progress
Village Coverage
Village Covered
1
T/W Progress
Required
1
Boring Done
1
Air Compressor Done
1
O.P. Unit Done
1
OHT Progress
Required
1
Work Started
1
Work Completed
1
Solar Plant
Required
23
Procured
23
KW
Work Status
Yes
Electric
Required
0
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
12778.00
Meter
Length Laid
11991.00
Meter
Scheme Assigned Villages
1 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Gautam Buddha Nagar | Dadari | Kudi Khera | 652319 | Kudi Khera | 346 | 343 | 99% | Work In Progress | Not Certified |