Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status |
|---|---|---|---|---|---|---|---|
| 1 | Sitapur | NCC Ltd. | 20097964 | BIJWAR KHURD JJM SCHEME | 536.12 | 292.97 | Not Integrated |
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 4 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 35 | 35 | Yes | 0 | NA | No | 26635.00 | 26635.00 |
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Sitapur | Khairabad | Qasimpur | 410540 | Qasimpur | 219 | 216 | 99 | Work In Progress | Not Certified |
| 2 | Sitapur | Khairabad | Umariya | 410553 | Umariya | 219 | 218 | 100 | Work In Progress | Not Certified |
| 3 | Sitapur | Khairabad | Bijwar Khurd | 410566 | Bijwar Khurd | 139 | 138 | 99 | Work In Progress | Not Certified |
| 4 | Sitapur | Khairabad | Bijwar Khurd | 410567 | Dhanipur | 205 | 195 | 95 | Work In Progress | Not Certified |