Scheme Details

S.No. District Name Agency Name Scheme Id Scheme Name Estimated Cost Expenditure Approve By Agency Status Approve By EE Status Automation Status
1 Ghaziabad LC INFRA 20097985 ALIPUR REORGANIZATION WATER SUPPLY SCHEME 150.79 42.68 Verified Verified view more

Scheme Assigne Villages

Sno. District Name Bolck Panchayat Village ID Village Name House Holds FHTC FHTC % Har Gar Jal Certified Handed Over Villages
1 Ghaziabad Loni Allipur Nauraspur 392346 Allipur 460 420 91 Work In Progress Not Certified Verified

Scheme Progress

Village Covered T/W OHT Solar Plant Electric Distribution (Line Laying in meter.)
Required Boring Done Air Compressor done O. P. Unit done Required Work Started Work Completed Required Procured (KW) Work status Required Transformer Procured Work status Total Length Length Laid
1 1 1 1 1 1 1 1 0 0 NA 10 NA No 5707.00 5300.00