Scheme Details
DISTRICT
Kaushambi
AGENCY
JMC - Lakshmi (JV)
SCHEME ID
20098065
SCHEME NAME
BAKORHA WATER SUPPLY SCHEME
ESTIMATED COST
203.99
EXPENDITURE
7.96
AUTOMATION STATUS
Not Integrated
SCHEME STATUS
Trial Run
Scheme Physical Progress
Village Coverage
Village Covered
2
T/W Progress
Required
1
Boring Done
1
Air Compressor Done
0
O.P. Unit Done
0
OHT Progress
Required
1
Work Started
1
Work Completed
1
Solar Plant
Required
0
Procured
0
KW
Work Status
NA
Electric
Required
8
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
6026.00
Meter
Length Laid
5100.00
Meter
Scheme Assigned Villages
Village-wise FHTC, Har Ghar Jal and Certification Status
2 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Kaushambi | Kaushambi | Bakorha | 431351 | Piyuli Asanatpur | 109 | 83 | 76% | Work In Progress | Not Certified |
| 2 | Kaushambi | Kaushambi | Bakorha | 431352 | Bakorha | 204 | 193 | 95% | Work In Progress | Not Certified |