Scheme Details
DISTRICT
Meerut
AGENCY
Power Mech Projects Ltd
SCHEME ID
20098111
SCHEME NAME
JATAULA
ESTIMATED COST
115.83
EXPENDITURE
114.18
AUTOMATION STATUS
Live
View Live Screen
SCHEME STATUS
Operation & Maintenance
Scheme Physical Progress
Village Coverage
Village Covered
1
T/W Progress
Required
1
Boring Done
1
Air Compressor Done
1
O.P. Unit Done
1
OHT Progress
Required
0
Work Started
0
Work Completed
0
Solar Plant
Required
0
Procured
0
KW
Work Status
NA
Electric
Required
11
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
2841.00
Meter
Length Laid
2820.00
Meter
Scheme Assigned Villages
Village-wise FHTC, Har Ghar Jal and Certification Status
1 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Meerut | Rohata | Jataula | 391690 | Jataula | 204 | 204 | 100% | Har Ghar Jal | Certified |