Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status | 
|---|---|---|---|---|---|---|---|
| 1 | Amethi | Vindhya-GAJA (JV) | 20098316 | MAHAUNA PURAB & SARIYA PAIJAD Water Supply Scheme | 828.31 | 365.04 | Not Integrated | 
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 2 | 2 | 2 | 2 | 2 | 1 | 1 | 1 | 54 | 54 | Yes | 0 | NA | No | 25313.00 | 24287.00 | 
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified | 
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Amethi | Shukul Bazar | Sarayapirjada | 439176 | Sariya Peerjada | 283 | 226 | 80 | Work In Progress | Not Certified | 
| 2 | Amethi | Shukul Bazar | Mahauna Purab | 439179 | Mahauna Purab | 738 | 648 | 88 | Work In Progress | Not Certified |