Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status | 
|---|---|---|---|---|---|---|---|
| 1 | Sitapur | NCC Ltd. | 20098337 | JARELI JJM SCHEME | 947.66 | 280.32 | Not Integrated | 
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 2 | 2 | 2 | 2 | 2 | 1 | 1 | 0 | 56 | 56 | Yes | 0 | NA | No | 27937.00 | 27200.00 | 
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified | 
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Sitapur | Parsendi | Jareli | 410478 | Jareli | 1137 | 1115 | 98 | Work In Progress | Not Certified | 
| 2 | Sitapur | Parsendi | Mohraiya Kala | 410502 | Mohraiya Kala | 312 | 307 | 98 | Work In Progress | Not Certified |