Scheme Details
DISTRICT
Sitapur
AGENCY
NCC Ltd.
SCHEME ID
20098337
SCHEME NAME
JARELI JJM SCHEME
ESTIMATED COST
947.66
EXPENDITURE
313.91
AUTOMATION STATUS
Not Integrated
SCHEME STATUS
Trial Run
Scheme Physical Progress
Village Coverage
Village Covered
2
T/W Progress
Required
2
Boring Done
2
Air Compressor Done
2
O.P. Unit Done
2
OHT Progress
Required
1
Work Started
1
Work Completed
1
Solar Plant
Required
56
Procured
56
KW
Work Status
Yes
Electric
Required
0
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
27937.00
Meter
Length Laid
27200.00
Meter
Scheme Assigned Villages
Village-wise FHTC, Har Ghar Jal and Certification Status
2 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Sitapur | Parsendi | Jareli | 410478 | Jareli | 1137 | 1115 | 98% | Work In Progress | Not Certified |
| 2 | Sitapur | Parsendi | Mohraiya Kala | 410502 | Mohraiya Kala | 312 | 307 | 98% | Work In Progress | Not Certified |