Scheme Details
S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Approve By Agency Status | Approve By EE Status | Automation Status |
---|---|---|---|---|---|---|---|---|---|
1 | Sitapur | NCC Ltd. | 20098343 | BHAWANIPUR JJM SCHEME | 256.68 | 218.00 | Verified | Verified | Not Integrated |
Scheme Assigne Villages
Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified | Handed Over Villages |
---|---|---|---|---|---|---|---|---|---|---|---|
1 | Sitapur | Khairabad | Bhawanipur William Sahab | 410562 | Bhawanipur William Saheb | 73 | 60 | 82 | Work In Progress | Not Certified | Not Verified |
2 | Sitapur | Khairabad | Bhawanipur William Sahab | 410563 | Khubpur | 101 | 100 | 99 | Work In Progress | Not Certified | Verified |
3 | Sitapur | Khairabad | Bhawanipur William Sahab | 410564 | Sahsapur | 179 | 169 | 94 | Work In Progress | Not Certified | Not Verified |
4 | Sitapur | Khairabad | Bhawanipur William Sahab | 680699 | Ismailpur | 174 | 150 | 86 | Work In Progress | Not Certified | Not Verified |
Scheme Progress
Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
4 | 1 | 1 | 1 | 1 | 1 | 1 | 0 | 18 | 18 | Yes | 0 | NA | No | 8402.00 | 8000.00 |