Scheme Details
DISTRICT
Shamli
AGENCY
Gayatri Projects LTD
SCHEME ID
20098368
SCHEME NAME
Kabdaut & Butrari Water Supply Scheme Reorganisation
ESTIMATED COST
614.61
EXPENDITURE
335.58
AUTOMATION STATUS
Live
View Live Screen
SCHEME STATUS
Operation & Maintenance
Scheme Physical Progress
Village Coverage
Village Covered
2
T/W Progress
Required
3
Boring Done
3
Air Compressor Done
3
O.P. Unit Done
3
OHT Progress
Required
1
Work Started
1
Work Completed
1
Solar Plant
Required
59
Procured
59
KW
Work Status
Yes
Electric
Required
0
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
15.67
Meter
Length Laid
15669.00
Meter
Scheme Assigned Villages
Village-wise FHTC, Har Ghar Jal and Certification Status
2 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Shamli | Shamli | Kabraut | 384912 | Kabraut | 447 | 447 | 100% | Har Ghar Jal | Certified |
| 2 | Shamli | Shamli | Butrari | 384917 | Butrari | 464 | 464 | 100% | Har Ghar Jal | Certified |