Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status |
|---|---|---|---|---|---|---|---|
| 1 | Sitapur | NCC Ltd. | 20098393 | RAIPUR JJM SCHEME | 237.00 | 140.79 | Not Integrated |
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 3 | 1 | 1 | 1 | 1 | 1 | 1 | 0 | 18 | 18 | Yes | 0 | NA | No | 7373.00 | 6947.00 |
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Sitapur | Maholi | RAIPUR | 409783 | Behra | 190 | 189 | 99 | Work In Progress | Not Certified |
| 2 | Sitapur | Maholi | RAIPUR | 409784 | Raipur | 233 | 230 | 99 | Work In Progress | Not Certified |
| 3 | Sitapur | Maholi | RAIPUR | 680798 | Sahebpur | 55 | 51 | 93 | Work In Progress | Not Certified |