Scheme Details
DISTRICT
Sitapur
AGENCY
NCC Ltd.
SCHEME ID
20098410
SCHEME NAME
SONSARI JJM SCHEME
ESTIMATED COST
264.98
EXPENDITURE
137.54
AUTOMATION STATUS
Not Integrated
SCHEME STATUS
Under Construction
Scheme Physical Progress
Village Coverage
Village Covered
2
T/W Progress
Required
1
Boring Done
1
Air Compressor Done
1
O.P. Unit Done
1
OHT Progress
Required
1
Work Started
1
Work Completed
0
Solar Plant
Required
18
Procured
18
KW
Work Status
Yes
Electric
Required
0
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
11265.00
Meter
Length Laid
11100.00
Meter
Scheme Assigned Villages
Village-wise FHTC, Har Ghar Jal and Certification Status
2 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Sitapur | Behta | Chandi | 410809 | Ahirori Semariya | 140 | 139 | 99% | Work In Progress | Not Certified |
| 2 | Sitapur | Behta | Sonsari | 410848 | Sonsari | 262 | 261 | 100% | Work In Progress | Not Certified |