Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status |
|---|---|---|---|---|---|---|---|
| 1 | Balrampur | Dara- Eco Protection (JV) | 20098448 | PIPRA JAMUNI WATER SUPPLY SCHEME | 344.26 | 60.47 | Not Integrated |
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 3 | 1 | 1 | 1 | 1 | 1 | 0 | 0 | 27 | 27 | No | 0 | NA | No | 22686.00 | 22000.00 |
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Balrampur | Pachperwa | Pipra Jamuni | 444114 | Pipra Jamuni | 345 | 330 | 96 | Work In Progress | Not Certified |
| 2 | Balrampur | Pachperwa | Pipra Jamuni | 444115 | Narchahwa Sanoman | 109 | 94 | 86 | Work In Progress | Not Certified |
| 3 | Balrampur | Pachperwa | Pipra Jamuni | 444116 | Faruhwa | 97 | 93 | 96 | Work In Progress | Not Certified |