Scheme Details
DISTRICT
Ghazipur
AGENCY
Larsen & Toubro Ltd
SCHEME ID
20098515
SCHEME NAME
SHAHBAZPUR W/S SCHEME
ESTIMATED COST
187.05
EXPENDITURE
94.07
AUTOMATION STATUS
Live
View Live Screen
SCHEME STATUS
Operation & Maintenance
Scheme Physical Progress
Village Coverage
Village Covered
2
T/W Progress
Required
1
Boring Done
1
Air Compressor Done
1
O.P. Unit Done
1
OHT Progress
Required
1
Work Started
1
Work Completed
1
Solar Plant
Required
11
Procured
11
KW
Work Status
Yes
Electric
Required
0
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
7867.58
Meter
Length Laid
5703.00
Meter
Scheme Assigned Villages
Village-wise FHTC, Har Ghar Jal and Certification Status
3 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Ghazipur | Kasimabad | Shahbazpur | 473271 | Shahbazpur | 120 | 120 | 100% | Har Ghar Jal | Certified |
| 2 | Ghazipur | Kasimabad | Shahbazpur | 473272 | Urev | 77 | 77 | 100% | Har Ghar Jal | Certified |
| 3 | Ghazipur | Kasimabad | Shahbazpur | 473273 | Jagdishpur M. Shahbazpur | 5 | 5 | 100% | Har Ghar Jal | Not Certified |