Scheme Details
DISTRICT
Budaun
AGENCY
PNC-SPML-JV
SCHEME ID
20098564
SCHEME NAME
Mohshampur anandpur water supply scheme
ESTIMATED COST
264.09
EXPENDITURE
86.78
AUTOMATION STATUS
Not Integrated
SCHEME STATUS
Under Construction
Scheme Physical Progress
Village Coverage
Village Covered
4
T/W Progress
Required
1
Boring Done
1
Air Compressor Done
1
O.P. Unit Done
1
OHT Progress
Required
1
Work Started
0
Work Completed
0
Solar Plant
Required
13
Procured
13
KW
Work Status
Yes
Electric
Required
0
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
9235.00
Meter
Length Laid
9235.00
Meter
Scheme Assigned Villages
Village-wise FHTC, Har Ghar Jal and Certification Status
4 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Budaun | Mion | Mohshampur Anandpur | 402400 | Mohshampur Anandpur | 119 | 115 | 97% | Work In Progress | Not Certified |
| 2 | Budaun | Mion | Mohshampur Anandpur | 402401 | Gadhaula Urf Jartoli | 55 | 55 | 100% | Har Ghar Jal | Not Certified |
| 3 | Budaun | Mion | Mohshampur Anandpur | 402402 | Sakatpur | 85 | 85 | 100% | Har Ghar Jal | Not Certified |
| 4 | Budaun | Mion | Mohshampur Anandpur | 402403 | SIMARIA DEDU | 78 | 78 | 100% | Har Ghar Jal | Not Certified |