Track Your Scheme

Know your scheme details, physical progress and current status

Scheme Details
DISTRICT Budaun
AGENCY PNC-SPML-JV
SCHEME ID 20098566
SCHEME NAME kheda jalalpur kham & sidhauli kham water supply scheme
ESTIMATED COST 347.60
EXPENDITURE 139.40
AUTOMATION STATUS Not Integrated
SCHEME STATUS Under Construction
Scheme Physical Progress
Village Coverage
Village Covered 3
T/W Progress
Required 1
Boring Done 1
Air Compressor Done 1
O.P. Unit Done 1
OHT Progress
Required 1
Work Started 1
Work Completed 0
Solar Plant
Required 20
Procured 20 KW
Work Status Yes
Electric
Required 0
Transformer Procured NA
Work Status No
Distribution Line
Total Length 20685.00 Meter
Length Laid 20600.00 Meter

Scheme Assigned Villages

Village-wise FHTC, Har Ghar Jal and Certification Status

3 Villages
Sno. District Block Panchayat Village ID Village Name Households FHTC FHTC % Har Ghar Jal Certified
1 Budaun Usawan Kheda Jalalpur Kham 402539 Kheda Jalalpur Kham 60 57 95% Work In Progress Not Certified
2 Budaun Usawan Kheda Jalalpur Kham 402540 Jata 115 109 95% Work In Progress Not Certified
3 Budaun Usawan Sidhauli Kham 402546 Sidhauli Kham 90 90 100% Har Ghar Jal Not Certified