Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status |
|---|---|---|---|---|---|---|---|
| 1 | Varanasi | Larsen & Toubro Ltd | 20098798 | Basantpur Water Supply Scheme | 254.17 | 119.57 | Not Integrated |
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 5 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 18 | 18 | Yes | 0 | NA | No | 16611.00 | 16579.00 |
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Varanasi | Arajiline | Basantpur | 476323 | Basantpur | 70 | 69 | 99 | Work In Progress | Not Certified |
| 2 | Varanasi | Arajiline | Basantpur | 476324 | Kamaalpur | 73 | 71 | 97 | Work In Progress | Not Certified |
| 3 | Varanasi | Arajiline | Basantpur | 476325 | Nagaipur | 70 | 69 | 99 | Work In Progress | Not Certified |
| 4 | Varanasi | Arajiline | Basantpur | 476326 | Mechakanpur | 34 | 28 | 82 | Work In Progress | Not Certified |
| 5 | Varanasi | Arajiline | Basantpur | 476327 | Tarsaanv | 82 | 70 | 85 | Work In Progress | Not Certified |