Scheme Details
DISTRICT
Varanasi
AGENCY
Larsen & Toubro Ltd
SCHEME ID
20098831
SCHEME NAME
Rampur Water Supply Scheme
ESTIMATED COST
260.06
EXPENDITURE
89.96
AUTOMATION STATUS
Not Integrated
SCHEME STATUS
Under Construction
Scheme Physical Progress
Village Coverage
Village Covered
5
T/W Progress
Required
1
Boring Done
1
Air Compressor Done
1
O.P. Unit Done
1
OHT Progress
Required
1
Work Started
1
Work Completed
0
Solar Plant
Required
11
Procured
0
KW
Work Status
NA
Electric
Required
0
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
22030.00
Meter
Length Laid
16523.00
Meter
Scheme Assigned Villages
Village-wise FHTC, Har Ghar Jal and Certification Status
5 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Varanasi | KASHI VIDYAPEETH | RAMPUR | 476617 | MIRAPUR | 58 | 38 | 66% | Work In Progress | Not Certified |
| 2 | Varanasi | KASHI VIDYAPEETH | RAMPUR | 476618 | JAGMA | 17 | 2 | 12% | Work In Progress | Not Certified |
| 3 | Varanasi | KASHI VIDYAPEETH | RAMPUR | 476619 | RAMPUR | 110 | 84 | 76% | Work In Progress | Not Certified |
| 4 | Varanasi | KASHI VIDYAPEETH | RAMPUR | 657691 | NIVIYA | 13 | 9 | 69% | Work In Progress | Not Certified |
| 5 | Varanasi | KASHI VIDYAPEETH | RAMPUR | 657695 | SADALPUR | 153 | 131 | 86% | Work In Progress | Not Certified |