Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status | 
|---|---|---|---|---|---|---|---|
| 1 | Jaunpur | AFCONS | 20098918 | MUKUNDOPUR VILLAGE WATER SUPPLY SCHEME | 315.02 | 129.41 | Not Integrated | 
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 4 | 1 | 1 | 1 | 1 | 1 | 1 | 0 | 20 | 20 | Yes | 0 | NA | No | 14412.00 | 12547.00 | 
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified | 
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Jaunpur | Sikrara | Bhuwa Khurd | 470029 | Bhuwa Khurd | 142 | 135 | 95 | Work In Progress | Not Certified | 
| 2 | Jaunpur | Sikrara | Mukundipur | 470031 | Mukundcpur | 128 | 127 | 99 | Work In Progress | Not Certified | 
| 3 | Jaunpur | Sikrara | Mukundipur | 470032 | Maheshpur | 46 | 44 | 96 | Work In Progress | Not Certified | 
| 4 | Jaunpur | Sikrara | Bhuwa Khurd | 470033 | Kamdeopur | 46 | 42 | 91 | Work In Progress | Not Certified |