Scheme Details
DISTRICT
Bahraich
AGENCY
GA INFRA-VPL
SCHEME ID
20098950
SCHEME NAME
TULSIPUR BALAHA (VPL) PWS
ESTIMATED COST
208.15
EXPENDITURE
62.95
AUTOMATION STATUS
Not Integrated
SCHEME STATUS
Trial Run
Scheme Physical Progress
Village Coverage
Village Covered
1
T/W Progress
Required
1
Boring Done
1
Air Compressor Done
1
O.P. Unit Done
1
OHT Progress
Required
1
Work Started
1
Work Completed
0
Solar Plant
Required
16
Procured
16
KW
Work Status
Yes
Electric
Required
0
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
6644.00
Meter
Length Laid
6600.00
Meter
Scheme Assigned Villages
Village-wise FHTC, Har Ghar Jal and Certification Status
1 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Bahraich | Balaha | Tulsipur | 441834 | Tulsipur | 256 | 256 | 100% | Har Ghar Jal | Not Certified |