Scheme Details
DISTRICT Bahraich
AGENCY GA INFRA-VPL
SCHEME ID 20099014
SCHEME NAME BANWARI GOPALPUR CHITAURA (VPL) MVS PWS
ESTIMATED COST 335.80
EXPENDITURE 162.72
AUTOMATION STATUS
SCHEME STATUS Operation & Maintenance
Scheme Physical Progress
Village Coverage
Village Covered 2
T/W Progress
Required 1
Boring Done 1
Air Compressor Done 1
O.P. Unit Done 1
OHT Progress
Required 1
Work Started 1
Work Completed 1
Solar Plant
Required 23
Procured 23 KW
Work Status Yes
Electric
Required 0
Transformer Procured NA
Work Status No
Distribution Line
Total Length 12193.00 Meter
Length Laid 12180.00 Meter

Scheme Assigned Villages

Village-wise FHTC, Har Ghar Jal and Certification Status

2 Villages
Sno. District Block Panchayat Village ID Village Name Households FHTC FHTC % Har Ghar Jal Certified
1 Bahraich Chitaura Banwari Gopalpur 442073 Banwari Gopalpur 295 295 100% Har Ghar Jal Not Certified
2 Bahraich Chitaura Banwari Gopalpur 442074 Jhansa 182 182 100% Har Ghar Jal Not Certified