Track Your Scheme

Know your scheme details, physical progress and current status

Scheme Details
DISTRICT Bahraich
AGENCY GA INFRA-VPL
SCHEME ID 20099017
SCHEME NAME MEERPUR KASBA CHITAURA (VPL) MVS PWS
ESTIMATED COST 429.42
EXPENDITURE 184.07
AUTOMATION STATUS Not Integrated
SCHEME STATUS Trial Run
Scheme Physical Progress
Village Coverage
Village Covered 2
T/W Progress
Required 1
Boring Done 1
Air Compressor Done 1
O.P. Unit Done 1
OHT Progress
Required 1
Work Started 0
Work Completed 1
Solar Plant
Required 37
Procured 37 KW
Work Status Yes
Electric
Required 0
Transformer Procured NA
Work Status No
Distribution Line
Total Length 11084.00 Meter
Length Laid 6832.00 Meter

Scheme Assigned Villages

Village-wise FHTC, Har Ghar Jal and Certification Status

2 Villages
Sno. District Block Panchayat Village ID Village Name Households FHTC FHTC % Har Ghar Jal Certified
1 Bahraich Chitaura Meerpur Kasba 442060 Meerpur Kasba 1030 1030 100% Har Ghar Jal Not Certified
2 Bahraich Chitaura Meerpur Kasba 442061 Andhra Chak 63 63 100% Har Ghar Jal Not Certified