Scheme Details
DISTRICT
Bahraich
AGENCY
GA INFRA-VPL
SCHEME ID
20099022
SCHEME NAME
SORAHIYA, SUJAOLI AND LAKSHMANPUR SALARPUR NAWABGANJ (VPL) MVS PWS
ESTIMATED COST
720.85
EXPENDITURE
175.94
AUTOMATION STATUS
Not Integrated
SCHEME STATUS
Under Construction
Scheme Physical Progress
Village Coverage
Village Covered
3
T/W Progress
Required
2
Boring Done
2
Air Compressor Done
2
O.P. Unit Done
2
OHT Progress
Required
2
Work Started
1
Work Completed
0
Solar Plant
Required
0
Procured
0
KW
Work Status
NA
Electric
Required
25
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
35586.00
Meter
Length Laid
32000.00
Meter
Scheme Assigned Villages
Village-wise FHTC, Har Ghar Jal and Certification Status
3 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Bahraich | Nawabganj | Lakhamanpur Salarpur | 441771 | Lakhamanpur Salarpur | 502 | 350 | 70% | Work In Progress | Not Certified |
| 2 | Bahraich | Nawabganj | Sorahiya | 441772 | Sorahiya | 1172 | 810 | 69% | Work In Progress | Not Certified |
| 3 | Bahraich | Nawabganj | Sujaoli | 441774 | Sujauli | 360 | 271 | 75% | Work In Progress | Not Certified |