Scheme Details
DISTRICT
Gonda
AGENCY
KLSR - RAYS (JV)
SCHEME ID
20099066
SCHEME NAME
BHABHNAN WSS
ESTIMATED COST
202.03
EXPENDITURE
58.38
AUTOMATION STATUS
Not Integrated
SCHEME STATUS
Under Construction
Scheme Physical Progress
Village Coverage
Village Covered
1
T/W Progress
Required
1
Boring Done
1
Air Compressor Done
1
O.P. Unit Done
1
OHT Progress
Required
1
Work Started
0
Work Completed
0
Solar Plant
Required
16
Procured
16
KW
Work Status
Yes
Electric
Required
0
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
8238.00
Meter
Length Laid
7655.00
Meter
Scheme Assigned Villages
Village-wise FHTC, Har Ghar Jal and Certification Status
1 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Gonda | Chhapia | Babhanan | 446288 | Babhanan | 305 | 305 | 100% | Har Ghar Jal | Not Certified |