Scheme Details
DISTRICT
Deoria
AGENCY
Rithwik-Koya (JV)
SCHEME ID
20099092
SCHEME NAME
Badhauna Hardo G.P. Water Supply Scheme
ESTIMATED COST
170.94
EXPENDITURE
151.30
AUTOMATION STATUS
Live
View Live Screen
SCHEME STATUS
Operation & Maintenance
Scheme Physical Progress
Village Coverage
Village Covered
3
T/W Progress
Required
1
Boring Done
1
Air Compressor Done
1
O.P. Unit Done
1
OHT Progress
Required
1
Work Started
1
Work Completed
1
Solar Plant
Required
16
Procured
16
KW
Work Status
Yes
Electric
Required
0
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
4910.00
Meter
Length Laid
6600.00
Meter
Scheme Assigned Villages
Village-wise FHTC, Har Ghar Jal and Certification Status
3 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Deoria | Bhagalpur | BADHOUNA HARDO | 460202 | Chak Tikait | 1 | 1 | 100% | Har Ghar Jal | Certified |
| 2 | Deoria | Bhagalpur | BADHOUNA HARDO | 460205 | Barhouna Hardo | 184 | 184 | 100% | Har Ghar Jal | Certified |
| 3 | Deoria | Bhagalpur | BADHOUNA HARDO | 697374 | UJARA BADHAUNA | 4 | 4 | 100% | Har Ghar Jal | Certified |