Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status | 
|---|---|---|---|---|---|---|---|
| 1 | Rampur | OMIL-JWIL (JV) | 20099132 | RUSTAMPUR MV W/S SCHEME | 183.30 | 60.37 | Not Integrated | 
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 5 | 1 | 1 | 1 | 1 | 1 | 1 | 0 | 12 | 12 | Yes | 0 | NA | No | 13988.00 | 14580.00 | 
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified | 
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Rampur | Bilaspur | RUSTAMPUR | 389517 | JAMNAPUR | 53 | 47 | 89 | Work In Progress | Not Certified | 
| 2 | Rampur | Bilaspur | RUSTAMPUR | 389521 | Rustampur | 56 | 52 | 93 | Work In Progress | Not Certified | 
| 3 | Rampur | Bilaspur | RUSTAMPUR | 389522 | BHOLAPUR QADIM | 40 | 32 | 80 | Work In Progress | Not Certified | 
| 4 | Rampur | Bilaspur | RUSTAMPUR | 389523 | ALWA NAGLA | 36 | 23 | 64 | Work In Progress | Not Certified | 
| 5 | Rampur | Bilaspur | RUSTAMPUR | 389524 | SARDHARPUR | 28 | 21 | 75 | Work In Progress | Not Certified |