Follow us on for latest updates.    |    To Lodge Complaint Call On 18001212164   or   visit   www.jalsamadhan.in


Track Your Scheme

Know your scheme details, physical progress and current status

Scheme Details
DISTRICT Deoria
AGENCY LC INFRA
SCHEME ID 20099172
SCHEME NAME RO-REORGANISATION OF PATHARDEWA GROUP OF VILLAGES WATER SUPPLY SCHEME
ESTIMATED COST 602.66
EXPENDITURE 208.44
AUTOMATION STATUS Not Integrated
SCHEME STATUS Under Construction
Scheme Physical Progress
Village Coverage
Village Covered 2
T/W Progress
Required 2
Boring Done 2
Air Compressor Done 2
O.P. Unit Done 2
OHT Progress
Required 2
Work Started 1
Work Completed 1
Solar Plant
Required 0
Procured 0 KW
Work Status NA
Electric
Required 0
Transformer Procured NA
Work Status No
Distribution Line
Total Length 29701.00 Meter
Length Laid 40000.00 Meter

Scheme Assigned Villages

Village-wise FHTC, Har Ghar Jal and Certification Status

2 Villages
Sno. District Block Panchayat Village ID Village Name Households FHTC FHTC % Har Ghar Jal Certified
1 Deoria Pathardewa Pathardewa 459036 Pathardewa 1103 1103 100% Har Ghar Jal Not Certified
2 Deoria Pathardewa Bhelipatti 459038 Bhelipatti 339 339 100% Har Ghar Jal Not Certified