Scheme Details
DISTRICT
Deoria
AGENCY
LC INFRA
SCHEME ID
20099175
SCHEME NAME
RO-REORGANISATION MADANPUR GROUP OF VILLAGES WATER SUPPLY SCHEME
ESTIMATED COST
918.16
EXPENDITURE
414.79
AUTOMATION STATUS
Not Integrated
SCHEME STATUS
Trial Run
Scheme Physical Progress
Village Coverage
Village Covered
5
T/W Progress
Required
2
Boring Done
2
Air Compressor Done
2
O.P. Unit Done
2
OHT Progress
Required
2
Work Started
2
Work Completed
0
Solar Plant
Required
20
Procured
20
KW
Work Status
Yes
Electric
Required
0
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
23102.00
Meter
Length Laid
23000.00
Meter
Scheme Assigned Villages
Village-wise FHTC, Har Ghar Jal and Certification Status
7 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Deoria | Rudrapur | Madanpur | 459786 | Madanpur | 1878 | 1878 | 100% | Har Ghar Jal | Not Certified |
| 2 | Deoria | Rudrapur | Madanpur | 459787 | Sabdalpur | 15 | 15 | 100% | Har Ghar Jal | Not Certified |
| 3 | Deoria | Rudrapur | Madanpur | 459788 | Kamupur | 21 | 19 | 90% | Work In Progress | Not Certified |
| 4 | Deoria | Rudrapur | Ramaipura | 459794 | Ramaipura | 182 | 178 | 98% | Work In Progress | Not Certified |
| 5 | Deoria | Rudrapur | Ramaipura | 459795 | Malpatti | 93 | 86 | 92% | Work In Progress | Not Certified |
| 6 | Deoria | Rudrapur | Keotalia | 459842 | Keotalia | 291 | 277 | 95% | Work In Progress | Not Certified |
| 7 | Deoria | Rudrapur | Keotalia | 459843 | Patwania | 35 | 35 | 100% | Har Ghar Jal | Not Certified |