Scheme Details
S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Approve By Agency Status | Approve By EE Status | Automation Status |
---|---|---|---|---|---|---|---|---|---|
1 | Deoria | LC INFRA | 20099175 | RO-REORGANISATION MADANPUR GROUP OF VILLAGES WATER SUPPLY SCHEME | 918.16 | 234.48 | Verified | Verified | Not Integrated |
Scheme Assigne Villages
Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified | Handed Over Villages |
---|---|---|---|---|---|---|---|---|---|---|---|
1 | Deoria | Rudrapur | Madanpur | 459786 | Madanpur | 1878 | 1878 | 100 | Har Gar Jal | Not Certified | Verified |
2 | Deoria | Rudrapur | Madanpur | 459787 | Sabdalpur | 15 | 15 | 100 | Har Gar Jal | Not Certified | Verified |
3 | Deoria | Rudrapur | Madanpur | 459788 | Kamupur | 21 | 19 | 90 | Work In Progress | Not Certified | Verified |
4 | Deoria | Rudrapur | Keotalia | 459842 | Keotalia | 291 | 277 | 95 | Work In Progress | Not Certified | Not Verified |
5 | Deoria | Rudrapur | Keotalia | 459843 | Patwania | 35 | 35 | 100 | Har Gar Jal | Not Certified | Not Verified |
Scheme Progress
Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
5 | 2 | 2 | 2 | 2 | 2 | 2 | 0 | 20 | 20 | Yes | 0 | NA | No | 23102.00 | 23000.00 |