Scheme Details
DISTRICT
Bijnor
AGENCY
Vindhya-GAJA (JV)
SCHEME ID
20099314
SCHEME NAME
UMRA BUJURG WSS
ESTIMATED COST
250.63
EXPENDITURE
163.40
AUTOMATION STATUS
Not Integrated
SCHEME STATUS
Under Construction
Scheme Physical Progress
Village Coverage
Village Covered
2
T/W Progress
Required
1
Boring Done
1
Air Compressor Done
1
O.P. Unit Done
1
OHT Progress
Required
1
Work Started
1
Work Completed
0
Solar Plant
Required
16
Procured
16
KW
Work Status
Yes
Electric
Required
0
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
7421.00
Meter
Length Laid
6880.00
Meter
Scheme Assigned Villages
Village-wise FHTC, Har Ghar Jal and Certification Status
3 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Bijnor | Noorpur | Pauti | 387548 | Alauddinpur | 167 | 90 | 54% | Work In Progress | Not Certified |
| 2 | Bijnor | Noorpur | Umra Bujurg | 387635 | Umra Bujurg | 228 | 228 | 100% | Har Ghar Jal | Not Certified |
| 3 | Bijnor | Noorpur | Heempur Prithia | 387638 | Hempurprathi1a | 210 | 210 | 100% | Har Ghar Jal | Not Certified |