Track Your Scheme

Know your scheme details, physical progress and current status

Scheme Details
DISTRICT Kanpur Dehat
AGENCY VSA
SCHEME ID 20099329
SCHEME NAME Baijamau Bangar
ESTIMATED COST 355.10
EXPENDITURE 151.85
AUTOMATION STATUS Not Integrated
SCHEME STATUS Trial Run
Scheme Physical Progress
Village Coverage
Village Covered 3
T/W Progress
Required 1
Boring Done 1
Air Compressor Done 1
O.P. Unit Done 1
OHT Progress
Required 1
Work Started 0
Work Completed 1
Solar Plant
Required 30
Procured 30 KW
Work Status Yes
Electric
Required 0
Transformer Procured NA
Work Status No
Distribution Line
Total Length 12588.00 Meter
Length Laid 12588.00 Meter

Scheme Assigned Villages

Village-wise FHTC, Har Ghar Jal and Certification Status

3 Villages
Sno. District Block Panchayat Village ID Village Name Households FHTC FHTC % Har Ghar Jal Certified
1 Kanpur Dehat Rajpur Baijamau Bangar 421827 Baijamau Bangar 203 202 100% Work In Progress Not Certified
2 Kanpur Dehat Rajpur Baijamau Bangar 421828 Arsun Bangar 156 155 99% Work In Progress Not Certified
3 Kanpur Dehat Rajpur Baijamau Bangar 421829 Bichhawani Bangar 89 88 99% Work In Progress Not Certified