Scheme Details
DISTRICT
Ambedkar Nagar
AGENCY
Vindhya-GAJA (JV)
SCHEME ID
20099359
SCHEME NAME
Asopur Water Supply Scheme
ESTIMATED COST
1153.24
EXPENDITURE
930.88
AUTOMATION STATUS
Not Integrated
SCHEME STATUS
Under Construction
Scheme Physical Progress
Village Coverage
Village Covered
7
T/W Progress
Required
2
Boring Done
2
Air Compressor Done
2
O.P. Unit Done
2
OHT Progress
Required
1
Work Started
0
Work Completed
0
Solar Plant
Required
86
Procured
86
KW
Work Status
Yes
Electric
Required
0
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
46258.00
Meter
Length Laid
43620.00
Meter
Scheme Assigned Villages
Village-wise FHTC, Har Ghar Jal and Certification Status
7 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Ambedkar Nagar | Tanda | Husainpur Sudhana | 437493 | Husainpur Sudhana | 376 | 370 | 98% | Work In Progress | Not Certified |
| 2 | Ambedkar Nagar | Tanda | Asopur | 437496 | Asopur | 923 | 919 | 100% | Work In Progress | Not Certified |
| 3 | Ambedkar Nagar | Tanda | Asopur | 437497 | Rustampur | 112 | 110 | 98% | Work In Progress | Not Certified |
| 4 | Ambedkar Nagar | Tanda | Asopur | 437498 | Chak Asopur | 89 | 89 | 100% | Har Ghar Jal | Not Certified |
| 5 | Ambedkar Nagar | Tanda | Hakeempur | 437500 | Shareefpur | 56 | 56 | 100% | Har Ghar Jal | Not Certified |
| 6 | Ambedkar Nagar | Tanda | Daulatpur Kaji | 437635 | Daulatpur Kaji | 175 | 173 | 99% | Work In Progress | Not Certified |
| 7 | Ambedkar Nagar | Tanda | Daulatpur Kaji | 437637 | MOJANPUR | 134 | 134 | 100% | Har Ghar Jal | Not Certified |