Scheme Details
DISTRICT
Rampur
AGENCY
SPML Infra
SCHEME ID
20099373
SCHEME NAME
Bosena & Bairkhera MV Water Supply Scheme
ESTIMATED COST
312.65
EXPENDITURE
149.74
AUTOMATION STATUS
Not Integrated
SCHEME STATUS
Under Construction
Scheme Physical Progress
Village Coverage
Village Covered
3
T/W Progress
Required
1
Boring Done
1
Air Compressor Done
1
O.P. Unit Done
1
OHT Progress
Required
1
Work Started
1
Work Completed
0
Solar Plant
Required
0
Procured
0
KW
Work Status
NA
Electric
Required
25
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
17411.00
Meter
Length Laid
13100.00
Meter
Scheme Assigned Villages
Village-wise FHTC, Har Ghar Jal and Certification Status
3 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Rampur | Bilaspur | Bair Khera | 389700 | Bair Khera | 212 | 197 | 93% | Work In Progress | Not Certified |
| 2 | Rampur | Bilaspur | Bosena | 389709 | Bosena | 223 | 214 | 96% | Work In Progress | Not Certified |
| 3 | Rampur | Bilaspur | Bosena | 389710 | Gularia Tuela | 158 | 147 | 93% | Work In Progress | Not Certified |