DISTRICT Fatehpur
AGENCY GA INFRA - BABA (JV)
SCHEME ID 20099417
SCHEME NAME SANGAON W/S
ESTIMATED COST 586.54
EXPENDITURE 286.17
AUTOMATION STATUS Not Integrated
SCHEME STATUS Under Construction
Scheme Physical Progress
Village Coverage
Village Covered 1
T/W Progress
Required 2
Boring Done 2
Air Compressor Done 2
O.P. Unit Done 2
OHT Progress
Required 1
Work Started 1
Work Completed 0
Solar Plant
Required 0
Procured 0 KW
Work Status NA
Electric
Required 15
Transformer Procured NA
Work Status No
Distribution Line
Total Length 19540.00 Meter
Length Laid 17985.00 Meter

Scheme Assigned Villages

Village-wise FHTC, Har Ghar Jal and Certification Status

2 Villages
Sno. District Block Panchayat Village ID Village Name Households FHTC FHTC % Har Ghar Jal Certified
1 Fatehpur Teliyani Sangaon 427790 Sangaon 1498 1498 100% Har Ghar Jal Not Certified
2 Fatehpur Teliyani Sangaon 427791 Puretaz Mahmood 192 143 74% Work In Progress Not Certified