Scheme Details
DISTRICT
Fatehpur
AGENCY
GA INFRA - BABA (JV)
SCHEME ID
20099429
SCHEME NAME
Aung (RO)
ESTIMATED COST
579.75
EXPENDITURE
286.60
AUTOMATION STATUS
Not Integrated
SCHEME STATUS
Under Construction
Scheme Physical Progress
Village Coverage
Village Covered
2
T/W Progress
Required
2
Boring Done
2
Air Compressor Done
2
O.P. Unit Done
2
OHT Progress
Required
1
Work Started
1
Work Completed
1
Solar Plant
Required
39
Procured
39
KW
Work Status
No
Electric
Required
0
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
18470.00
Meter
Length Laid
16246.00
Meter
Scheme Assigned Villages
Village-wise FHTC, Har Ghar Jal and Certification Status
2 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Fatehpur | Malwan | Aung | 427420 | Aung | 706 | 645 | 91% | Work In Progress | Not Certified |
| 2 | Fatehpur | Malwan | Aung | 427421 | Keechakpur | 88 | 88 | 100% | Har Ghar Jal | Not Certified |