Scheme Details
DISTRICT
Fatehpur
AGENCY
GA INFRA - BABA (JV)
SCHEME ID
20099441
SCHEME NAME
Mauyara (RO)
ESTIMATED COST
374.01
EXPENDITURE
188.36
AUTOMATION STATUS
Not Integrated
SCHEME STATUS
Under Construction
Scheme Physical Progress
Village Coverage
Village Covered
1
T/W Progress
Required
1
Boring Done
1
Air Compressor Done
1
O.P. Unit Done
1
OHT Progress
Required
1
Work Started
1
Work Completed
1
Solar Plant
Required
23
Procured
23
KW
Work Status
Yes
Electric
Required
0
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
18250.00
Meter
Length Laid
16151.00
Meter
Scheme Assigned Villages
Village-wise FHTC, Har Ghar Jal and Certification Status
1 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Fatehpur | Hathgaon | Mauyara | 428303 | Maupara | 508 | 508 | 100% | Har Ghar Jal | Not Certified |