Scheme Details
DISTRICT
Bijnor
AGENCY
Vindhya-GAJA (JV)
SCHEME ID
20099446
SCHEME NAME
MANDORI WSS
ESTIMATED COST
451.58
EXPENDITURE
341.56
AUTOMATION STATUS
Not Integrated
SCHEME STATUS
Under Construction
Scheme Physical Progress
Village Coverage
Village Covered
3
T/W Progress
Required
1
Boring Done
1
Air Compressor Done
1
O.P. Unit Done
1
OHT Progress
Required
1
Work Started
0
Work Completed
0
Solar Plant
Required
36
Procured
36
KW
Work Status
Yes
Electric
Required
0
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
14469.00
Meter
Length Laid
10672.81
Meter
Scheme Assigned Villages
Village-wise FHTC, Har Ghar Jal and Certification Status
3 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Bijnor | Budhanpur | Mandori | 387200 | Safi1abad | 396 | 396 | 100% | Har Ghar Jal | Not Certified |
| 2 | Bijnor | Budhanpur | Mandori | 387201 | Girdharpur | 252 | 252 | 100% | Har Ghar Jal | Not Certified |
| 3 | Bijnor | Budhanpur | Mandori | 703002 | MANDORI | 385 | 385 | 100% | Har Ghar Jal | Not Certified |