Scheme Details
DISTRICT
Ayodhya
AGENCY
UNIVERSAL MEP
SCHEME ID
20099478
SCHEME NAME
SHAHWAZ CHAK WSS
ESTIMATED COST
146.93
EXPENDITURE
146.84
AUTOMATION STATUS
Live
View Live Screen
SCHEME STATUS
Operation & Maintenance
Scheme Physical Progress
Village Coverage
Village Covered
1
T/W Progress
Required
1
Boring Done
1
Air Compressor Done
1
O.P. Unit Done
1
OHT Progress
Required
1
Work Started
1
Work Completed
1
Solar Plant
Required
13
Procured
13
KW
Work Status
Yes
Electric
Required
0
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
4630.00
Meter
Length Laid
4630.00
Meter
Scheme Assigned Villages
Village-wise FHTC, Har Ghar Jal and Certification Status
1 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Ayodhya | Mavai | Sah Bachak | 436216 | Shahbaj Chak | 120 | 120 | 100% | Har Ghar Jal | Certified |