Scheme Details
DISTRICT
Saharanpur
AGENCY
GA INFRA - BABA (JV)
SCHEME ID
20099505
SCHEME NAME
Kaluwala Jahanpur
ESTIMATED COST
726.39
EXPENDITURE
311.63
AUTOMATION STATUS
Not Integrated
SCHEME STATUS
Under Construction
Scheme Physical Progress
Village Coverage
Village Covered
1
T/W Progress
Required
1
Boring Done
1
Air Compressor Done
1
O.P. Unit Done
1
OHT Progress
Required
1
Work Started
1
Work Completed
1
Solar Plant
Required
30
Procured
30
KW
Work Status
Yes
Electric
Required
0
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
29798.00
Meter
Length Laid
25000.00
Meter
Scheme Assigned Villages
Village-wise FHTC, Har Ghar Jal and Certification Status
1 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Saharanpur | Muzaffarabad | Kaluwala Jahanpur | 383522 | Kaluwala Jahanpur | 2676 | 2649 | 99% | Work In Progress | Not Certified |