Scheme Details
DISTRICT
Sitapur
AGENCY
NCC Ltd.
SCHEME ID
20099534
SCHEME NAME
Gaur Chaukadia,Guniya Khurd & Phulpur Guniya water supply Scheme
ESTIMATED COST
567.49
EXPENDITURE
257.00
AUTOMATION STATUS
Not Integrated
SCHEME STATUS
Under Construction
Scheme Physical Progress
Village Coverage
Village Covered
5
T/W Progress
Required
1
Boring Done
1
Air Compressor Done
1
O.P. Unit Done
1
OHT Progress
Required
1
Work Started
1
Work Completed
0
Solar Plant
Required
35
Procured
35
KW
Work Status
Yes
Electric
Required
0
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
19580.00
Meter
Length Laid
19580.00
Meter
Scheme Assigned Villages
Village-wise FHTC, Har Ghar Jal and Certification Status
5 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Sitapur | Behta | Gaur Chaukhariya | 410769 | Gaur Chaukhdia | 316 | 313 | 99% | Work In Progress | Not Certified |
| 2 | Sitapur | Behta | Gaur Chaukhariya | 410770 | Harkhee Behar | 146 | 145 | 99% | Work In Progress | Not Certified |
| 3 | Sitapur | Behta | Guniya Khurd | 410771 | Ametiya | 109 | 107 | 98% | Work In Progress | Not Certified |
| 4 | Sitapur | Behta | Guniya Khurd | 410772 | Guniya Khurd | 138 | 135 | 98% | Work In Progress | Not Certified |
| 5 | Sitapur | Behta | Pulpur Guniya | 410773 | Pulpur Guniya | 313 | 313 | 100% | Har Ghar Jal | Not Certified |