Scheme Details
DISTRICT
Sitapur
AGENCY
NCC Ltd.
SCHEME ID
20099543
SCHEME NAME
Shah Jalapur & Sultanpur Kamaicha
ESTIMATED COST
593.50
EXPENDITURE
352.84
AUTOMATION STATUS
Not Integrated
SCHEME STATUS
Operation & Maintenance
Scheme Physical Progress
Village Coverage
Village Covered
3
T/W Progress
Required
1
Boring Done
1
Air Compressor Done
1
O.P. Unit Done
1
OHT Progress
Required
1
Work Started
1
Work Completed
1
Solar Plant
Required
42
Procured
42
KW
Work Status
Yes
Electric
Required
0
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
22647.00
Meter
Length Laid
22647.00
Meter
Scheme Assigned Villages
Village-wise FHTC, Har Ghar Jal and Certification Status
3 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Sitapur | Khairabad | Shah Jalalpur | 410633 | Krishnapur | 39 | 36 | 92% | Work In Progress | Not Certified |
| 2 | Sitapur | Khairabad | Shah Jalalpur | 410636 | Shah Jalalpur | 706 | 701 | 99% | Work In Progress | Not Certified |
| 3 | Sitapur | Khairabad | Sultanpur Kamaicha | 410640 | Sultanpur Kamaicha | 474 | 472 | 100% | Work In Progress | Not Certified |