Scheme Details
S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Approve By Agency Status | Approve By EE Status | Automation Status |
---|---|---|---|---|---|---|---|---|---|
1 | Bahraich | PNC-SPML-JV | 20099558 | DEEHA ASHOKA CHITTAURA RF MVS PWS | 186.57 | 53.81 | Verified | Verified | view more |
Scheme Assigne Villages
Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified | Handed Over Villages |
---|---|---|---|---|---|---|---|---|---|---|---|
1 | Bahraich | Chitaura | Deeha | 442139 | Deeha | 470 | 470 | 100 | Har Gar Jal | Certified | Verified |
2 | Bahraich | Chitaura | Ashoka | 442140 | Ashoka | 283 | 283 | 100 | Har Gar Jal | Certified | Verified |
3 | Bahraich | Chitaura | Ashoka | 442141 | Suha Para | 178 | 178 | 100 | Har Gar Jal | Certified | Verified |
4 | Bahraich | Chitaura | Ashoka | 442142 | Sansar Para | 133 | 133 | 100 | Har Gar Jal | Certified | Verified |
5 | Bahraich | Chitaura | Ashoka | 442143 | Gaura | 13 | 13 | 100 | Har Gar Jal | Certified | Verified |
Scheme Progress
Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
5 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 23 | 0 | Yes | 0 | NA | No | 5666.00 | 5666.00 |