Follow us on for latest updates.    |    To Lodge Complaint Call On 18001212164   or   visit   www.jalsamadhan.in


Track Your Scheme

Know your scheme details, physical progress and current status

Scheme Details
DISTRICT Bahraich
AGENCY PNC-SPML-JV
SCHEME ID 20099561
SCHEME NAME BANGLACHAK & JAHANCHAK RISIA RO MVS PWS
ESTIMATED COST 594.08
EXPENDITURE 150.32
AUTOMATION STATUS Not Integrated
SCHEME STATUS Under Construction
Scheme Physical Progress
Village Coverage
Village Covered 3
T/W Progress
Required 2
Boring Done 2
Air Compressor Done 2
O.P. Unit Done 2
OHT Progress
Required 2
Work Started 2
Work Completed 1
Solar Plant
Required 30
Procured 30 KW
Work Status Yes
Electric
Required 0
Transformer Procured NA
Work Status No
Distribution Line
Total Length 19867.00 Meter
Length Laid 19867.00 Meter

Scheme Assigned Villages

3 Villages
Sno. District Block Panchayat Village ID Village Name Households FHTC FHTC % Har Ghar Jal Certified
1 Bahraich Risia BANGLA CHAK 441992 BANGLA CHAK 1188 1183 100% Work In Progress Not Certified
2 Bahraich Risia BANGLA CHAK 441993 JAHAN CHAK 77 58 75% Work In Progress Not Certified
3 Bahraich Risia Babhni 441998 Teliya 37 37 100% Har Ghar Jal Not Certified