Scheme Details
DISTRICT
Siddharth Nagar
AGENCY
VSA
SCHEME ID
20099604
SCHEME NAME
BANKATA FIRST WSS
ESTIMATED COST
512.62
EXPENDITURE
321.23
AUTOMATION STATUS
Not Integrated
SCHEME STATUS
Under Construction
Scheme Physical Progress
Village Coverage
Village Covered
8
T/W Progress
Required
2
Boring Done
2
Air Compressor Done
2
O.P. Unit Done
2
OHT Progress
Required
1
Work Started
1
Work Completed
1
Solar Plant
Required
37
Procured
37
KW
Work Status
Yes
Electric
Required
0
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
21011.00
Meter
Length Laid
21011.00
Meter
Scheme Assigned Villages
9 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Siddharth Nagar | Mithwal | Kamharia | 447315 | Kamharia | 130 | 123 | 95% | Work In Progress | Not Certified |
| 2 | Siddharth Nagar | Khesraha | Baranwar | 447617 | Baranwar | 171 | 171 | 100% | Har Ghar Jal | Not Certified |
| 3 | Siddharth Nagar | Khesraha | Baranwar | 447618 | Sorwamafi | 98 | 98 | 100% | Har Ghar Jal | Not Certified |
| 4 | Siddharth Nagar | Khesraha | Baranwar | 447619 | Urwalia | 8 | 8 | 100% | Har Ghar Jal | Not Certified |
| 5 | Siddharth Nagar | Khesraha | Bankata First | 447696 | Bankata Eirst | 159 | 159 | 100% | Har Ghar Jal | Not Certified |
| 6 | Siddharth Nagar | Khesraha | Rohanua | 447698 | Padia Buzurg | 53 | 53 | 100% | Har Ghar Jal | Not Certified |
| 7 | Siddharth Nagar | Khesraha | Rohanua | 447699 | Kamharia | 44 | 44 | 100% | Har Ghar Jal | Not Certified |
| 8 | Siddharth Nagar | Khesraha | Rohanua | 447700 | Rohua | 102 | 102 | 100% | Har Ghar Jal | Not Certified |
| 9 | Siddharth Nagar | Khesraha | Bankata First | 447701 | Murilamisir | 72 | 68 | 94% | Work In Progress | Not Certified |