Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status |
|---|---|---|---|---|---|---|---|
| 1 | Jaunpur | Welspun Kaveri Infraprojects JV | 20099652 | Uttar Gawan | 431.40 | 56.67 | Not Integrated |
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 4 | 1 | 1 | 1 | 1 | 1 | 1 | 0 | 35 | 35 | No | 0 | NA | No | 26015.00 | 25459.00 |
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Jaunpur | Dharmapur | Kadeepur | 470424 | Kadeepur | 113 | 112 | 99 | Work In Progress | Not Certified |
| 2 | Jaunpur | Dharmapur | Kadeepur | 470425 | Pauna | 135 | 133 | 99 | Work In Progress | Not Certified |
| 3 | Jaunpur | Dharmapur | Kadeepur | 470426 | Tulsipur | 39 | 31 | 79 | Work In Progress | Not Certified |
| 4 | Jaunpur | Dharmapur | Uttar Gawan | 470431 | Uttar Gawan | 431 | 267 | 62 | Work In Progress | Not Certified |