Scheme Details
DISTRICT
Siddharth Nagar
AGENCY
VSA
SCHEME ID
20099659
SCHEME NAME
ITWA BAKSI & PIPRI BUJURG & SUHEELWA WSS
ESTIMATED COST
617.00
EXPENDITURE
262.29
AUTOMATION STATUS
Not Integrated
SCHEME STATUS
Under Construction
Scheme Physical Progress
Village Coverage
Village Covered
6
T/W Progress
Required
2
Boring Done
2
Air Compressor Done
2
O.P. Unit Done
2
OHT Progress
Required
1
Work Started
1
Work Completed
1
Solar Plant
Required
58
Procured
58
KW
Work Status
Yes
Electric
Required
0
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
18602.00
Meter
Length Laid
18254.00
Meter
Scheme Assigned Villages
Village-wise FHTC, Har Ghar Jal and Certification Status
6 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Siddharth Nagar | Itwa | Pipri Bujurg | 448193 | Pipri Bujurg | 310 | 301 | 97% | Work In Progress | Not Certified |
| 2 | Siddharth Nagar | Itwa | Itwa Baksi | 448194 | Itwa Baksi | 251 | 251 | 100% | Har Ghar Jal | Not Certified |
| 3 | Siddharth Nagar | Itwa | Itwa Baksi | 448195 | Pipri Lagri | 54 | 51 | 94% | Work In Progress | Not Certified |
| 4 | Siddharth Nagar | Itwa | Itwa Baksi | 448196 | Mudila Vish Datt | 146 | 144 | 99% | Work In Progress | Not Certified |
| 5 | Siddharth Nagar | Itwa | Suhelwa | 448198 | Suhelwa | 173 | 164 | 95% | Work In Progress | Not Certified |
| 6 | Siddharth Nagar | Itwa | Itwa Baksi | 656492 | Nauwagav | 178 | 171 | 96% | Work In Progress | Not Certified |