Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status | 
|---|---|---|---|---|---|---|---|
| 1 | Jaunpur | AFCONS | 20099769 | Maideeh & Salarpur Village Water Supply Scheme | 483.61 | 142.37 | Not Integrated | 
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 4 | 1 | 1 | 1 | 1 | 1 | 0 | 1 | 37 | 37 | Yes | 0 | NA | No | 21332.00 | 18542.00 | 
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified | 
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Jaunpur | Mariyahun | Mai Deeh | 469795 | Mai Deeh | 295 | 204 | 69 | Work In Progress | Not Certified | 
| 2 | Jaunpur | Mariyahun | Mai Deeh | 469796 | Gopalpur | 20 | 16 | 80 | Work In Progress | Not Certified | 
| 3 | Jaunpur | Mariyahun | Salar Pur | 469850 | Salarpur | 151 | 102 | 68 | Work In Progress | Not Certified | 
| 4 | Jaunpur | Mariyahun | Salar Pur | 469851 | Rampur Nisfi | 46 | 23 | 50 | Work In Progress | Not Certified |