Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status | 
|---|---|---|---|---|---|---|---|
| 1 | Bahraich | GA INFRA-VPL | 20099796 | MEHARBAN NAGAR BALAHA (VPL) MVS PWS | 476.44 | 3.99 | Not Integrated | 
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 2 | 1 | 0 | 0 | 0 | 1 | 1 | 0 | 37 | 37 | Yes | 0 | NA | No | 17583.00 | 11000.00 | 
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified | 
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Bahraich | Balaha | Meharban Nagar | 441812 | Meharban Nagar | 508 | 508 | 100 | Har Gar Jal | Not Certified | 
| 2 | Bahraich | Balaha | Balha | 441813 | Balha | 505 | 337 | 67 | Work In Progress | Not Certified |