Scheme Details
DISTRICT
Pratapgarh
AGENCY
JMC - Lakshmi (JV)
SCHEME ID
20099902
SCHEME NAME
Hathaura Sarai Water Supply Scheme
ESTIMATED COST
181.35
EXPENDITURE
0.00
AUTOMATION STATUS
Not Integrated
SCHEME STATUS
Under Construction
Scheme Physical Progress
Village Coverage
Village Covered
1
T/W Progress
Required
1
Boring Done
0
Air Compressor Done
0
O.P. Unit Done
0
OHT Progress
Required
1
Work Started
1
Work Completed
0
Solar Plant
Required
0
Procured
0
KW
Work Status
NA
Electric
Required
10
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
9488.00
Meter
Length Laid
0.00
Meter
Scheme Assigned Villages
Village-wise FHTC, Har Ghar Jal and Certification Status
1 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Pratapgarh | Shivgarh | Hathaura Sarai | 430559 | Hathaura Sarai | 197 | 184 | 93% | Work In Progress | Not Certified |