Scheme Details
DISTRICT Etawah
AGENCY OMIL-JWIL (JV)
SCHEME ID 20099912
SCHEME NAME KISHONPUR JADONPUR
ESTIMATED COST 211.87
EXPENDITURE 72.12
AUTOMATION STATUS Not Integrated
SCHEME STATUS Trial Run
Scheme Physical Progress
Village Coverage
Village Covered 4
T/W Progress
Required 1
Boring Done 1
Air Compressor Done 1
O.P. Unit Done 1
OHT Progress
Required 0
Work Started 0
Work Completed 0
Solar Plant
Required 0
Procured 0 KW
Work Status NA
Electric
Required 12
Transformer Procured NA
Work Status No
Distribution Line
Total Length 9997.00 Meter
Length Laid 9500.00 Meter

Scheme Assigned Villages

4 Villages
Sno. District Block Panchayat Village ID Village Name Households FHTC FHTC % Har Ghar Jal Certified
1 Etawah Badapura Kishonpur Jadonpur 419717 Kishonpur Jadonpur 214 207 97% Work In Progress Not Certified
2 Etawah Badapura Kishonpur Jadonpur 419718 Aarazi Jadhonpur 94 90 96% Work In Progress Not Certified
3 Etawah Badapura Kishonpur Jadonpur 419719 Jadhonpur 87 83 95% Work In Progress Not Certified
4 Etawah Badapura Kishonpur Jadonpur 419720 Rampur Naoli 214 205 96% Work In Progress Not Certified