Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status |
|---|---|---|---|---|---|---|---|
| 1 | Etawah | OMIL-JWIL (JV) | 20099925 | BHATPURA & KHEDA AJAB SINGH | 424.82 | 162.58 | Not Integrated |
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 3 | 2 | 2 | 1 | 1 | 2 | 0 | 0 | 46 | 46 | Yes | 0 | NA | No | 12670.00 | 11950.00 |
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Etawah | Badapura | KHEDA AZAB SINGH | 419634 | Kheda Azab Singh | 326 | 310 | 95 | Work In Progress | Not Certified |
| 2 | Etawah | Badapura | Bhatpura | 419641 | Bhatpura | 168 | 168 | 100 | Har Gar Jal | Not Certified |
| 3 | Etawah | Badapura | Bhatpura | 419642 | Paroli Mustkil Kamet | 157 | 126 | 80 | Work In Progress | Not Certified |